Saline County is moving forward with a remodeling project for part of the third floor in the city county building to accomodate two new district judges and a magistrate judge in the 28th Judicial District.
As part of the state budget for the current fiscal year, the judicial branch was provided funding to increase the number of district court judges across the state. This change brings with it the need for space for seven new courst dtaff and two new jury-ready courtrooms.
The County awarded a contract to Harbin Construction that included project contingencies and design fees.
Commissioners also approved a construction manager at risk, funded through ARPA allocations, for the courtrooms. Using a construction manager at risk is expected to help save time in project completion.
A look at how American Rescue Plan Act monies have addressed needs in Saline County 2/26/2023 Salina Journal
Public safety and criminal justice funds have gone toward addressing some existing needs and a surprise need after legislation brought three new judges into the 28th Judicial District Court last year. Read the Article
Building Renovation Update 2 2/24/2023 Saline County
On Monday we took advantage of an empty building to saw cut and remove the brick wall at the entrance to the new courtroom. Building Renovation Update 2 Article
Health Department and City-County Building are top priorities for future planning 2/23/2023 Salina Journal
Among other county properties, the dilapidated state of the Health Department building at 125 West Elm Street in Salina has become a concern among the county’s board of commissioners. Read the Article
Building Renovation Update 2/17/2023 Saline County
This week, crews worked hard getting the demolition on third floor close to 95 percent complete. Building Renovation Update Article
Saline County to remodel part of city county building for new judges 10/11/2022 Salina Journal